February construction news

4:14PM February 17, 2021

Yeddo

Our crews are diligently working on completing mainline construction in the Yeddo build area. Yeddo has experienced construction delays due to material demand and weather, but we estimate mainline construction to be finished in late February.

Virtual community night

A virtual community night will be held on February 24 at 6 p.m. to answer questions about service features and pricing, and streaming services. During this event, we'll also share how and when to place your order for service. Be sure to check your mail and email for more details!

Service installation

Steps 4 through 7 of our fiber construction process explaining what to expect during the fiber installation process.  


Wea

Mainline construction is expected to finish in mid-March. Once complete, this build will allow us to provide 100% fiber-optic internet service to approximately 220 members.

Virtual community night

A virtual community night is scheduled for Tuesday, March 16. More details are being sent via mail and email.

Register your interest

Be sure to register your interest at join.wintek.com so you can be among the first to know when you can order service.


Hillsboro

We are excited to announce that the construction of our 100% fiber-optic network has started in the Hillsboro build area.

Fiber construction

The Hillsboro build area is divided into 7 zones that follow geographical boundaries. To find your zone, enter your address here. The project entails over 33 miles of overhead construction.

Currently, electric crews are preparing the poles for the new fiber lines. Approximately 38 poles will need to be changed out for larger poles to add height or strength. Mainline construction started in February and is expected to be completed in late May.


Roberts 1 and 2

Our crews are busy preparing for mainline construction of our 100% fiber-optic network in the Roberts build area. When complete, the build will offer service to approximately 945 members. Roberts build area 1 is divided into 13 zones, while Roberts build area 2 has 16 zones. To find your zone, enter your address here.

Construction activity

Currently, electric crews are preparing the poles for the new fiber lines. Approximately 295 poles will need to be changed out for larger poles to add height or strength. Engineers are also preparing for the start of mainline construction. You may see crews walking through your area, taking photos, and gathering measurements. Mainline construction is expected to start in April and is estimated to be complete in late August.


Darlington 2

Our crews are busy preparing for mainline construction in the Darlington 2 build area. When complete, the build will allow us to serve approximately 123 members. The Darlington 2 area is divided into 6 zones that follow geographical boundaries. To find your zone, enter your address here. This project entails 18 miles of underground construction.

Construction activity

Currently, electric crews are preparing the poles for the new fiber lines. Approximately 54 poles will need to be changed out for larger poles to add height or strength. Engineers are also preparing for the start of mainline construction. You may see crews walking through your area, taking photos, and gathering measurements. Mainline construction is expected to start in late June and be completed by late September.


General information

Construction and installation process

There are multiple steps in the fiber construction and installation process. This information will help you understand the various phases of fiber construction.

In-home installation safety

Safe is our number one priority when we visit your home. To protect our customers and our employees, we’ll follow all CDC guidelines and recommendations. Learn about our in-home installation safety procedures.

About the service

Our fiber network offers symmetrical internet speeds up to 1 Gigabit per second (1,000 Mbps), allowing you to stream videos, play games online, and download and upload – on multiple devices – with ease and reliability. Our hassle-free internet has no hidden fees, no fine print and no contracts. With competitive pricing, unlimited usage, free installation, and local service and support, we’re confident that you’ll love Wintek powered by Tipmont fiber internet service.